Projects
Waste-Water Treatment Plant
Advisory Services to Prepare for Future Claim Dispute
KGC's Role
Hired by the Client to provide preliminary analysis, risk assessment and risk mitigation planning.
KGC’s Role
KGC was hired to examine the procurement method and costs associated with a replacement builder to remedy defective envelope workmanship.
Senior Residence
Rebuttal Report
New High End Custom Home
Construction Deficiencies Dispute
KGC’s Role
KGC undertook the role to assist Counsel to the Builder on what constituted “code defects” verses “deficiencies” with the associated quantum.
KGC’s Role
KGC Consulting was hired by the Owner to opine on several aspects of the delay related to subsoil impact factors and other scheduled disruptions.
Seniors Residence
Delay Claim

New Hospital Development
Schedule Delay Claim
Trade specialist contractor delayed several months as a result of extensive changes and lack of performance by other inter-dependent trade activity
Condominium High Rise
Schedule Delay Claim
Mechanical contractor delayed several months on scheduled installation


Condominium High Rise
Schedule Delay Claim
Formwork contractor delayed several months as a result of extensive geotechnical issues
Seniors Nursing Home
Rebuttal Report Defence
General contractor required assistance to defend against a multi-million dollar claim launched by a finishing trade contractor


Mid-Stream Energy Project
Schedule Delay & Damages Entitlement Claim
Lump sum piping commissioning subcontract, earned value dispute. Involving various work packages for several process systems
Affordable Housing Dispute
A project delay dispute associated with workmanship deficiencies arose between a general contractor and a municipal housing authority involved in constructing a multi-suite three-storey complex.


Civil Project
Schedule Delay Claim
Civil contractor installing massive retaining wall foundation system for a multi-national corporation.
Commercial Plaza Renovation
Schedule Delay Claim
Major exterior facade upgrades and interior renovations to a retail plaza.


Civil Experience - Piling & Caissons
The civil project involved a slope stabilization project for the installation of micropiles, caisson piles, tie-back anchors and shotcrete to protect the integrity of a public walking trail servicing a housing community to an adjacent green space.
High-Rise Office
Scope of Work Dispute and Schedule Delay Claim
Envelope subcontractor impacted by various root causes on multi-storey urban high-rise office project.


Cost and Scope of Work Housing Dispute
A dispute arose between a home renovation Contractor and the Owner after a verbal quote was provided by the Contractor for a significant scope of work.
Museum
Schedule Delay Claim
The museum features extensive gallery spaces angled onto a unique set of beetle pine timber 7-beam nodal trusses, two classrooms, a 60-seat Family Theatre, research and collections areas.


Hotel
Commercial Management Support
This 139 room Casino Hotel was a turnaround project effort involving KGC to assist First Nations Band Council.
Bridge Replacement
Schedule Delay Claim
This replacement bridge was a new 7-span steel girder structure resting on concrete caissons, grade beams and concrete diaphragm wall end bracing. KGC provided assistance to a trade contractor seeking to avoid liquidated damages

