Sample Projects

 Sample Projects

KGC's Role

Audit investigation of Contract Administration practices and invoicing documentation associated with a Construction Management CCDC 5B arrangement.

Winery Renovation

Project Financial Audit

 


Royal Alberta Museum

Museum Cladding - Envelope Claim & Counter Claim dispute

 

KGC's Role

Examine the financial Cause and Effect Impact to the panel supplier of uncoordinated constructability elements.

KGC's Role

Provide a cost-to-cure comparison report based on opposing multiple technical subject matter experts.

Custom Home

Mold Contamination & Workmanship Insurance Dispute

 


Solar Farm

Subject Matter Expert Report on Critical Path analysis.

KGC's Role

Retained by client’s counsel to opine on late arrival impact on Owner provided solar panels.

KGC's Role

Retained by client’s counsel to opine on valuation of deficiencies associated with General Contractor holdback.

Multi-Residential Facility

Subject Matter Expert Report on deficiencies for mediation.

 


Commercial Retail Complex

Interim and Final Delay Claim and Quantum Assessment

 

 

 

KGC's Role

Retained by envelope Subcontractor client to provide two separate reports for negotiation with General Contractor.

KGC's Role

Hired by the Client to provide preliminary analysis, risk assessment and risk mitigation planning.

Waste-Water Treatment Plant

Advisory Services to Prepare for Future Claim Dispute

 


Senior Residence

Rebuttal Report

 

KGC’s Role

KGC was hired to examine the procurement method and costs associated with a replacement builder to remedy defective envelope workmanship.

KGC’s Role

KGC undertook the role to assist Counsel to the Builder on what constituted “code defects” verses “deficiencies” with the associated quantum.

New High End Custom Home

Construction Deficiencies Dispute

 


Seniors Residence

Delay Claim

 

KGC’s Role

KGC Consulting was hired by the Owner to opine on several aspects of the delay related to subsoil impact factors and other scheduled disruptions.


New Hospital Development

Schedule Delay Claim

Trade specialist contractor delayed several months as a result of extensive changes and lack of performance by other inter-dependent trade activity
New Hospital Development

1 Condo - Schedule Delay Claim

Condominium High Rise

Schedule Delay Claim

Mechanical contractor delayed several months on scheduled installation

Condominium High Rise

Schedule Delay Claim

Formwork contractor delayed several months as a result of extensive geotechnical issues
Schedule Delay Claim - condo-high-rise

Picture2

Seniors Nursing Home

Rebuttal Report Defence

General contractor required assistance to defend against a multi-million dollar claim launched by a finishing trade contractor

Mid-Stream Energy Project

Schedule Delay & Damages Entitlement Claim

Lump sum piping commissioning subcontract, earned value dispute. Involving various work packages for several process systems
Mid-stream Energy Project

Affordable Housing

Affordable Housing Dispute

​​A project delay dispute associated with workmanship deficiencies arose between a general contractor and a municipal housing authority involved in constructing a multi-suite three-storey complex.

Civil Project

Schedule Delay Claim

Civil contractor installing massive retaining wall foundation system for a multi-national corporation.
NEW civil-project---schedule-delay

Richmond Sq

Commercial Plaza Renovation

Schedule Delay Claim

Major exterior facade upgrades and interior renovations to a retail plaza.

Civil Experience - Piling & Caissons

The civil project involved a slope stabilization project for the installation of micropiles, caisson piles, tie-back anchors and shotcrete to protect the integrity of a public walking trail servicing a housing community to an adjacent green space.
3 original-caissons

2 high-rise-office

High-Rise Office

Scope of Work Dispute and Schedule Delay Claim

Envelope subcontractor impacted by various root causes on multi-storey urban high-rise office project.
 

Cost and Scope of Work Housing Dispute

Envelope subcontractor impacted by various root causes on multi-storey urban high-rise office project.
 

 

 

 

2 original-cost-and-scope-of-wor

Museum

Museum

Schedule Delay Claim

The museum features extensive gallery spaces angled onto a unique set of beetle pine timber 7-beam nodal trusses, two classrooms, a 60-seat Family Theatre, research and collections areas
 

 


Hotel

Commercial Management Support

This 139 room Casino Hotel was a turnaround project effort involving KGC to assist First Nations Band Council.
2 original-hotel-dene---cold-lak

1 original-2017

Bridge Replacement

Schedule Delay Claim

This replacement bridge was a new 7-span steel girder structure resting on concrete caissons, grade beams and concrete diaphragm wall end bracing. KGC provided assistance to a trade contractor seeking to avoid liquidated damages

Civil Structure

Schedule Delay Claim

​​Flood Handling Upgrade in Southern Alberta. This project consisted of a new 42m x 84m long concrete-reinforced sloped spillway structure with interlocking sloped slabs, wing walls, raised and depressed chute and basin accessories.
1 oroginal-chain-lakes